Planning Timeline
Planning is a collaborative process and we start all of our projects by gaining an understanding of the site, the neighbourhood and the community we are working with. A successful project balances the ideas and inspiration from community stakeholders, in collaboration with good planning practice and professional expertise, to arrive at a viable plan for the future. We are designing our project to deliver a number of community benefits in alignment with the OCP and as our plans advance, we will share updates here.
Latest Information:
Presentation Council, 1st and 2nd Reading, May 16, 2022
Previous Presentations (Spring 2021)
Timeline
>Winter 2020/2021
Preliminary meetings
with Township of Esquimalt Staff
>Spring 2021
Conceptual Plan Development
April 6, 2021
Preliminary Planning Information
Project Information Website
April 21, 2021
Neighbourhood Information
Session #1
April 28, 2021
Neighbourhood Information
Session #2
Plan Refinement
Rezoning Application Submission
>Summer 2021
Township Review of Rezoning Application
Stakeholder Engagement
August 12, 2021
Open House and Virtual Open House
themarin.ca
>Fall 2021
Design Review Committee (DRC)
Advisory Planning Commission (APC)
Council Review and Direction
>Spring/Summer 2022
Rezoning Decision
Development Permit Application Preparation